Some key milestones have now been achieved on the $900mill upgrades to Warringah Road and Frenchs Forest Roads as part of the Northern Beaches Hospital Connectivity and Enhancement works.

Two pedestrian bridges have now been constructed across Stage 2-Warringah Road as well as asphalt laid on Warringah Road westbound in preparation for a major traffic switch in early 2018.

In Stage 1 – Frenchs Forest Road, service and drainage relocation is now complete with permanent pavement also completed adjacent to Northern Beaches Hospital.

Major works currently underway include capping beam and barrier slab construction in preparation of the 2 x slot excavations in Warringah Road

ESO is providing all the survey resources to this project which is conveniently located at the front of ESO’s Sydney office.

Construction of Stage 1 is due for completion in late 2018 and Stage 2 in late 2019.